UPDATE PROGRESS OF STEEM AMAL HOUSING PROJECT 5% - (JUNE 19, 2021) BY ENGINEER SPECIALIST
50% of this post payout is for @steem.amal program acceleration
UPDATE PROGRESS OF STEEM AMAL HOUSING PROJECT
The Steem Amal Housing Project has started this project for the first time, so for the sake of transparency and accountability for the ongoing development, I as a board member in charge of engineering will publish the progress of the development three times a week.
Saturday (19/06/2021), the progress achieved for the Steem Amal Housing Project is 5% of the plan, this progress refers to the work that has been completed, which are as follows :
- Cleaning Area (100%)
- Foundation work (65%)
For more clarity, let's look at the table that I share below.
Perspective | Display | Progress |
---|---|---|
Front | 5% | |
Right | 5% | |
Back | 5% | |
Left | 5% |
Project Name | Steem Amal Housing Project |
---|---|
Budget | Rp. Rp 65,000,000 |
Beneficiary | Samsul |
Address | Nibong, Syamtalira Bayu-North Aceh, Indonesia |
Note:
- Updates take place 3 times in one week
- All documents have been authorized by the relevant parties.
- Documents in the form of photos or writing must have permission from Steem Amal Indonesia.
Thank you
Engineer Specialist Steem Amal Indonesia
Cc : @anroja @el-nailul @radjasalman @nazarul @muzack1 @heriadi @irawandedy @miftahuddin @curiesea @sofian88 dan @ayijufridar
@klen.civil
FROM ZERO TO HERO
This post has been supported by A Dollar A Day administered by @pennsif...
Good Job....👍👍👍😊