WSP Official report: Ongoing Program Update (WPS)
Free Education Center
- Construction Progress
This free education center building has entered phase II, where the builder has completed the installation of a blue roof like the color of the steem promo symbol ordered directly from outside the area. About 80% of the construction has gone well.
Perspective | Present Condition |
---|---|
Front View | |
Front and Right View | |
Right View | |
Front and Left View | |
Left View |
Inside View | Inside View |
Electrical Installation | Electrical Installation |
Electrical Installation | Electrical Installation |
Project Name | Free Education Center |
---|---|
Beneficiary | Khairul Huda School Boarding |
Address | Syamtalira Aron, North Aceh - Indonesia |
After installing the roof, the electric current installation workers will enter in order to get enough light for the teaching and learning process at night. For more detailed construction developments can be directly seen in the link below.
World Smile Project : Construction of Free Education Center - Update November 09, 2021
- Financial and Expenditure
The Cash Book shows the current balance in the form of assets 155,011 SBD, 22,005 STEEM, 1,312,625 SP and TRX of 1,268,131. While the Expenditure column to date is 530 SBD, the SBD is used for the construction of the Free Education Center 500 SBD, and 30 SBD is allocated for Free Education Program Support for early childhood in Aceh Province through the @steemitcountry account. For the total revenue earned by the @worldsmile account, namely; Assets 685,011 SBD, 22,005 STEEM, 1,312,625 SP and TRX totaling 1,268,131
For a more detailed view of the world smile project cash flow, you can directly follow the link below.
GENERAL CASH BOOK 📚 @worldsmile ACCOUNT CHARITY | First Week of November 2021 Publication
Especially for the construction of the free education center building, the funds are sufficient, as originally planned, about 530 SBD with a market price of 100 thousand rupiah per one SBD.
Details of expenses can be seen in the table below.
From the financial table above, we can see that so far, the cost of building a free education center building has been absorbed by RP. 45.060.000, - with more than 85% construction progress. The remainder of the initial budget of RP. 7.940.000,-.
- Completion Planning
The construction of a free education center is planned to be completed in November to be able to continue other activities that have been included in the list of activities for the world smile project.
This is the report that I can convey as a team in the world smile project.
#club5050 😀
thank you for your support, hopefully the charity work that we do can run perfectly..
This post has been featured in the latest edition of Steem News...
thank you for your support in making wider publications
Good job 🤗
Luar biasa tidak terasa sudah hampir mencapai tujuan sukses terus pak
campaign program : #club5050 #club75 #club100 #worldsmileproject50pc
I have included this post in the 21th issue of Steem News Magazine For Steemit Platform | November 11, 2021.
I hope the process is over soon 🙏😀