Fort Galt - New Year's Update

in #real-estate6 years ago (edited)

Another year has come and gone and its time for another progress update. Our last newsletter went out as the foundation was being poured. Once that phase of construction was completed, the rainy season set in and it proved to be a particularly intense one. Work was postponed for a while and then resumed once things cleared up again. With the return of summer, the next phase commenced and the first floor’s frame is now standing. The workers will soon be proceeding to the second floor and we intend to have the entire building envelope finished this season so that we can be working indoors when the heavy rains return again.

0ba313a3-9226-4985-aee2-054cbbbda240.jpg

We’re in the middle of the summer tourism season now and Valdivia is bustling. Visitors are coming from all over the world to meet us and see the project and we’re always happy to receive more. Anyone making such plans can contact us through our website to arrange a meeting and make sure we avoid scheduling conflicts.

The Valdivia airport is open again after its maintenance closure and things there are back to normal. A shuttle service is available at the front doors to bring visitors into the city, at which point, we’re always happy to meet and help with settling-in. Work on the coastal road is also complete so the drive is paved all the way out to Fort Galt. It’s a scenic route that follows the coastline through a series of villages on the beach and takes about forty minutes. A shortcut route for trucks is scheduled to be paved next year, at which point, it will be suitable for all vehicles and will cut our drive in half.

One of our community members has been hard at work establishing a new construction company here. He has already built a workshop and is working on a trio of houses now, two of which will be available for rent and sale later upon completion. We’ll be sure to showcase his work on our website once the visuals are ready to share.

5c5e7c8f-1f86-456a-be29-7f310be939e6.jpg

On a lower note, tools were stolen from our construction site recently so we’re now upgrading security by installing security cameras and a guardhouse as well as a new fence and gate. Local law enforcement has been very supportive and even assigned a patrolman to keep an eye on our property while its occupied. The tools were replaced and work resumed after only a few days’ interruption.

With the closing of 2018, we got caught up on our taxes and collected community maintenance fees from lot owners. We initiated several improvement projects which include the replacement of our scenic overlook and a bridge in the common park area. A leak in the water line was discovered and is being repaired and we’re also setting up electricity and internet infrastructure to service some of the lots that are now being developed so that their occupants can go about their business without interruption.

Both the core of the residential building and its north wing have sold out but there are still a few rooms left in the south wing for anyone still wanting to jump in. Once the structure is complete, prices will be raised to reflect the added safety that new buyers will appreciate at that point. Our earliest adopters took a big risk on us and we’re happy to see their investments gain value as the community comes together.

1713088a-b094-4b1b-a31c-8f6b846828cb.jpg

Another update will go out once the framing work on the second floor is complete so until then, we look forward to hearing from you and would like to wish you all a very happy new year.

-The Fort Galt Team

www.fortgalt.com

Sort:  

Great to see an update on Fort Galt. I'd love to visit someday.

Some obvious questions.

Why is it going to take you a whole season to get a stick frame building up with only the outer skin?

Why wasn't the first thing built on the site a locking shed for your tools?

Why isn't someone living on this site 24/7?

It isn't going to take the whole season to get the envelope up. We should have that done in just a few months. The inside won't be done before it starts raining again though.
We had locking shipping containers for the tools. The thieves cut through the locks with a grinder.
The construction company is responsible for the tools and they chose to put their faith in their locks rather than guards. Now that local thieves have shown themselves though, the construction company has obviously had to reassess the risk level and they now accept that hiring a guard is worthwhile.

Hello @piedpiper! This is a friendly reminder that you have 3000 Partiko Points unclaimed in your Partiko account!

Partiko is a fast and beautiful mobile app for Steem, and it’s the most popular Steem mobile app out there! Download Partiko using the link below and login using SteemConnect to claim your 3000 Partiko points! You can easily convert them into Steem token!

https://partiko.app/referral/partiko

Dear piedpiper:

We are SteemBet, the next generation STEEM based gaming platform. We are honored to invite you to join our first fantastic dice game, which is just the beginning of SteemBet game series. Our dividend system has now launched. The prize pool has already accumulated 2,000 STEEM and more than 60 players have participated in staking mining token SBT. A huge reward of 40,000 STEEM is awaiting! Join us NOW with other 500 STEEM users to loot HUGE dividend reward!!

SteemBet Team

Official Website
https://steem-bet.com

Discord Server
https://discord.gg/95cBN3W

Telegram Group
https://t.me/steembet