WSP : Construction Progress Report from Water System and Public Latrine [January 29, 2022]

in STEEM FOR BETTERLIFE3 years ago
Note: 50% of Rewards to accelerate the construction of the Water System and Public Latrine @worldsmile account

poster_2022-01-29-061405.png

Construction Progress Report from Water System and Public Latrine

Today is January 29, 2022, of the 11 main work items on the construction of the water system and public latrine, 4 of them have been completed, namely bouwplank, footing or foundation, sloof and column. Meanwhile, 4 other works that are being worked on or nearing completion are wall, beam, floor and water tube.

The rest of the wall work is plastering and installing ceramics along with the installation of pipes and faucets, then for the beams, the rest of the work is only on casting concrete as an iron blanket. The floor work has just been carried out by raising the floor using stockpiled soil, so after the completion of this work there is casting and installation of ceramics on the floor.

The work on the water tube with a size of 3 x 1 meter is almost complete, and the rest of the work is for the installation of ceramics. Of all the items that have been, are being and have not been worked on, the technical analysis shows that the construction progress for the water system and public latrine is 43%.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingComplete
3.SloofComplete
4.ColumnComplete
5.WallAlmost complete
6.BeamAlmost complete
7.FloorAlmost complete
8.Water tubAlmost complete
9.RoofOn Progress
10.PaintingOn Progress
11.ElectricalOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front View20220129_173536.jpg
Front and Right View20220129_173601.jpg
Front and Left View20220129_173839.jpg
Back View20220129_173705.jpg
Right View20220129_173619.jpg
Left View20220129_173759.jpg
Back and Right View20220129_173631.jpg
Back and Left View20220129_173727.jpg

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve @bien

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 3 years ago 

Мне очень нравится твой проект! Молодец!

 3 years ago 

Thanks a lot

 3 years ago 

Felicidades en este gran proyecto amigo @klen.civil

 3 years ago 

Thanks

 3 years ago 

It gladdens my heart to know how far this project has gone!
Thank you for sharing the progress report.
I trust to give all the support I can for this project.

Success!

 3 years ago 

Thanks

 3 years ago 

goodluck for the project, bang! teurimong geunaseh keu label member di komunitas! 🙌

 3 years ago 

Sama²

@tipu curate

Va muy adelantado el proyecto

--

This is a manual curation from the @tipU Curation Project.