How to build a Wind Turbine part 1 (resin casts work Stator)
This is a 3.6m or 1.3Kw wind turbine build. The first stage here is the making of the alternator parts which consist of the Stator and Magnet Rotor parts. The first part to make is the coil winder to create the coils for the stator.
The coils are shaped to fit into the space as close fitting as possible which helps keep them spaced well
Each coil should be weighed to ensure the same length of copper is used
Eventually all the coils are done and positioned in place to allow soldering them together
Before the next stage a Stator Resin Cast Mould is needed to be made
Now showing the Stator Coils soldered and in the mould ready for the pour
Wait a little time to allow air bubbles to rise before placing the top piece of fibreglass before placing the lid.
Screw down the lid and allow the resin to cure
The Stator is removed, cleaned up and checked
The next stage is the Magnet Rotors to follow..