Official Report WSP : Contruction Progress of Free Education Center East Aceh 12% [August 11, 2022]
After the Site Clearing and Landing Altitude Measurement work item was carried out 6 days ago, and exactly today on August 11, 2022, the increase in construction progress of the Free Education Center building has reached 12% according to the technical analysis I did when supervising the the construction. Where the other main work item, namely footing, has reached 7% which is indicated by the casting of the work item for all footing which reaches a volume of 4.92 M3 of the total casting volume of 7.04 M3. The target for completion of footing work items will be completed within the next 1/2 working day. And after the footing work item is finished, I instruct the workers to continue the sloof and post work items which will take about 2 to 4 working days in the future. Apart from the construction progress figures from the Free Education Center for East Aceh, all the materials needed for footing, sloof and post work are available at the construction site. Below I attach a table of the main work items from the Free Education Center Development for East Aceh which I have analyzed according to the specifications of Indonesian construction techniques.
No | Type of Work | Persentase |
---|---|---|
1. | Site Clearing and Landing Altitude Measurement | 5/5 |
2. | Footing | 7/10 |
3. | Sloof | 0/10 |
4. | Round Floor Building | 0/8 |
5. | Post | 0/15 |
6. | Wall | 0/12 |
7. | Beam | 0/10 |
8. | Steel Truss Roof | 0/20 |
9. | Painting | 0/5 |
10. | Finishing | 0/5 |
Total Persentase | 12/100 |
So from a total of 10 main work items from the Free Education Center Construction for East Aceh whose funding source is from the World Smile Project INT, it can be concluded that the construction progress has reached 12% of the total which is marked by the completion of 1 work item, namely Site Clearing and Landing Altitude Measurement with 5 %, and there is work being done in the form of footing which has progress of 7% from 10% of the total. And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :
Front View | Back View |
Right View | Left View |
This is the progress report on the construction of the free education center for East Aceh which has started today as of August 11, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.
Project | Free Education Center |
---|---|
Type | Buiding Contruction |
Size or Dimention | 9 x 6 meter |
Address | Tanjong Punti village, Madat district, East Aceh |
Benefit recipients | Early Childhood |
Teacher | @steemitcountry |
East Aceh, August 11, 2022
@klen.civil
WSP Construction Supervisor
Thank you for the feedback!
With my pleasure
:)
Semoga Allah mudahkan
Amin
Excellent initiative and as always a very beautiful job to build not only hope but to see them materialized with this type of works
Thanks a lot dear
Excelente me encanta ver cuando inicia un proyecto y el rápido progreso que tiene el WSP para culminarlo.
Muchos éxitos, gran trabajo.