Official Report WSP : Contruction Progress of Free Education Center East Aceh 12% [August 11, 2022]

in STEEM FOR BETTERLIFE2 years ago

image.png

After the Site Clearing and Landing Altitude Measurement work item was carried out 6 days ago, and exactly today on August 11, 2022, the increase in construction progress of the Free Education Center building has reached 12% according to the technical analysis I did when supervising the the construction. Where the other main work item, namely footing, has reached 7% which is indicated by the casting of the work item for all footing which reaches a volume of 4.92 M3 of the total casting volume of 7.04 M3. The target for completion of footing work items will be completed within the next 1/2 working day. And after the footing work item is finished, I instruct the workers to continue the sloof and post work items which will take about 2 to 4 working days in the future. Apart from the construction progress figures from the Free Education Center for East Aceh, all the materials needed for footing, sloof and post work are available at the construction site. Below I attach a table of the main work items from the Free Education Center Development for East Aceh which I have analyzed according to the specifications of Indonesian construction techniques.

NoType of WorkPersentase
1.Site Clearing and Landing Altitude Measurement5/5
2.Footing7/10
3.Sloof0/10
4.Round Floor Building0/8
5.Post0/15
6.Wall0/12
7.Beam0/10
8.Steel Truss Roof0/20
9.Painting0/5
10.Finishing0/5
Total Persentase12/100

So from a total of 10 main work items from the Free Education Center Construction for East Aceh whose funding source is from the World Smile Project INT, it can be concluded that the construction progress has reached 12% of the total which is marked by the completion of 1 work item, namely Site Clearing and Landing Altitude Measurement with 5 %, and there is work being done in the form of footing which has progress of 7% from 10% of the total. And below I also attach several documents in the form of photos of the work carried out on the first day, namely as follows :

Current condition of Free Education Center Development for East Aceh
image.pngimage.png
Front ViewBack View
image.pngimage.png
Right ViewLeft View
Other documentation is in the form of photos of workers in activity and on site materials
image.png
image.pngimage.png
image.pngimage.png
image.pngimage.png

This is the progress report on the construction of the free education center for East Aceh which has started today as of August 11, 2022. Finally, I would like to say thank you to all the donors who have donated to every program from WSP, and we also extend our gratitude. convey to the steemit team via @steemcurator01 and @steemcurator02 who have supported the World Smile Project so far.

The link to the previous post concerns the progress of the Free Education Center construction for East Aceh
  1. Official Report WSP : Contruction Progress of Free Education Center East Aceh 5% [August 5, 2022]
Free Education Center Building Information for East Aceh (World Smile Project INT)
ProjectFree Education Center
TypeBuiding Contruction
Size or Dimention9 x 6 meter
AddressTanjong Punti village, Madat district, East Aceh
Benefit recipientsEarly Childhood
Teacher@steemitcountry

Cc : @pennsif @el-nailul @heriadi @irawandedy @mariana4ve @ubongudofot @patjewell @alanasteemit


East Aceh, August 11, 2022
@klen.civil
WSP Construction Supervisor

Sort:  
 2 years ago 

Thank you for the feedback!

 2 years ago 

With my pleasure

:)

 2 years ago 

Semoga Allah mudahkan

 2 years ago 

Amin

 2 years ago 

Excellent initiative and as always a very beautiful job to build not only hope but to see them materialized with this type of works

 2 years ago 

Thanks a lot dear

 2 years ago 

Excelente me encanta ver cuando inicia un proyecto y el rápido progreso que tiene el WSP para culminarlo.

Muchos éxitos, gran trabajo.

Coin Marketplace

STEEM 0.30
TRX 0.12
JST 0.033
BTC 63672.27
ETH 3126.79
USDT 1.00
SBD 3.87