WSP : Construction Progress Report from Water System and Public Latrine [January 11, 2022]

in STEEM FOR BETTERLIFE2 years ago (edited)
Note: 50% of Rewards to accelerate the construction of the Water System and Public Latrine @worldsmile account

image.png

Construction Progress Report from Water System and Public Latrine

Today is January 11, 2022, where all preparations regarding the construction of the Water System and Public Latrine have started, the main work is that at this time the Bouwplank has been installed by the workers and today the work will also continue under the name of excavation work for the construction. .

Apart from excavating the foundation, the workers will also continue to prepare and carry out the ironwork that will be carried out. For today's initial target, the work has reached a percentage of 2% of the total work carried out on the construction of the Water System and Public Latrine.

The following are the types of work that exist in the construction of the Water System and Public Latrine with information on the realization in the field in accordance with the applicable technical analysis.

Table of the main types of work from the construction of the Water System and Public Latriner
NumberType of workNotes
1.BouwplankComplete
2.FootingOn Progress
3.SloofOn Progress
4.ColumnOn Progress
5.BeamOn Progress
5.WallOn Progress
7.Water tubOn Progress
8.RoofOn Progress
9.PaintingOn Progress
10.ElectricalOn Progress
Design of Water System and Public Latrine Construction
image.png
Progress of Water System and Public Latrine Construction
PerspectivePresent Condiition
Front Viewimage.png
Front and Right Viewimage.png
Front and Left Viewimage.png
Right Viewimage.png
Left Viewimage.png
Back Viewimage.png
Back and Right Viewimage.png
Left and Right Viewimage.png

This is a construction report related to the construction of the Water System and Public Latrine to all donors of the World Smile Project, especially to the steemit team through @steemcurator01 and @steemcurator02 who have provided support so far, I have done this construction report in accordance with technical analysis prevailing in Indonesia.

MAIN INFORMATION FROM WORLD SMILE PROJECT
Project NameWater System and Public Latrin
BeneficiaryKumbang Village Community
AddressSyamtalira Aron, North Aceh - Indonesia
Mapwhat3words.com

Related Links


Note:


  • Construction progress reports are in accordance with technical analysis
  • Financial Report will be submitted by other WSP team
  • All documents have been authorized by the relevant parties
  • Documents in the form of photos or writing must have permission from World Smile Project team

Cc : @pennsif @el-nailul @heriadi @irawandedy @miftahuddin @sofian88 @mariana4ve

Thanks
@klen.civil


cropped_image (1).png

Sort:  
 2 years ago 
DescriptionYesNo
Plagiarism-
club100-
club75-
club5050-
#steemexlusive-
Verified User-
Using Bot-

wsp verif line copy.png

 2 years ago 

Semoga proyek yang di jalankan oleh akun amal worldsmile selalu berjalan dengan lancar

 2 years ago 

Aamiin

 2 years ago 

Я в восторге от такой работы!

 2 years ago 

Thanks

 2 years ago 

Mantap, masjid mnsh kumbang kan?

 2 years ago 

Yes
hehehe

 2 years ago 

Mantap bang tamelake beu jalan yang di rencanakan , mudah mudahan lancar pembanguan sistem air dan jamban.
#club75
#club100
😊

 2 years ago 

Thank you for sharing this update, it's work in progress and we are very much sure that it will see success. Thank you for sharing the update.

Coin Marketplace

STEEM 0.27
TRX 0.13
JST 0.032
BTC 62795.05
ETH 2941.10
USDT 1.00
SBD 3.55